Kinsley Group was engaged by VicTrack under a secondment arrangement to manage the construction delivery of four separate groups of Culverts in Beaufort as part of the Beaufort Flood Minimisation Strategy.
The project was funded by the Pyrenees Shire Council via sponsorship from Regional Development Victoria and included track, civil and structural engineering disciplines.
The construction works were carefully planned and completed during a scheduled rail occupation that had been locked in for works associated with the Regional Rail Link Project during January 2012 in order to minimise delivery costs and impacts on train operations.
Design/construction risk workshops were facilitated and site surveillance works performed by Kinsley Group representatives to ensure the project works were delivered safely, with minimal impacts on train operations and in accordance with the relevant standards and code requirements.